Home > Bond Project > What's Happening at Schools? > Bear Creek Elementary School  
Bear Creek Elementary School 
Front of Bear Creek School 
 
Bear Creek Elementary School
2500 Table Mesa Drive
Boulder, Colorado 80305
720.561.3500
http://bvsd.org/schools/bearcreek/
Original construction date: 1970
Report Updated:  3/10/2010 
Project Details

Principal: Kent Cruger

Project Manager: Steve Schumacher

Architect: RTA

Contractor: Adolfson & Peterson

Project Budget: $6,457,529

Bear Creek project expenditures

Bond Program expenditures

 

Design Advisory Team (DAT):

Staff
Kent Cruger, Principal
Laurie Brockway
Emily Weller
Lucy Ewing
Cheryl Winter
Renie Cantrick
James Soole
Beth Sheveland
Mary Sue Rogers (also neighbor)

Parents/Community Members
Juana Gomez
Kellie Zell
Jon Ouellette 

Meeting Schedule
Sept. 14, 28, 3:30 - 5:30 p.m.
Oct. 12, 24, 3:30 - 5:30 p.m.
Oct. 12, 6 p.m. Neighbor meeting
Nov. 9, 30, 3:30 - 5:30 p.m.

Meeting Minutes

Contact the DAT 

Project Timeline

Scheduled Milestones
uSD (schematic design) due 11/09; Complete 11/09
uDD (design development) drawings due 12/09; Completed 12/09
uCD (construction documents) due 03/10
uConstruction Bid due 04/10
uConstruction Scheduled 06/10 - 07/11

u= Design phase
u= Construction bidding
u= Construction phase

Project Status
IT improvements are complete. The professional design team is working on construction documents. Project is on schedule.
 
 
 
Scope of Work

Facility Condition Assessment (FCA):

  • Clock and intercom upgrades
  • Interior finish upgrades (ceiling tiles, paint carpet, flooring, etc.)
  • Electrical service and distribution improvements
  • Roof replacement and repair
  • Landscape irrigation replacement and repair
  • Interior Signage Program

Program Compatibility Assessment (PCA):

  • Enlarge gym and remodel
  • Provide classroom additions and remodel
  • Enlarge library and computer room
  • Expand administration office and health room
  • Music, science, and art room additions and remodel
  • Reconfigure kindergartens
  • Expand cafeteria
  • Parking lot and drop-off improvements

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs