Skip to main content
Home

Bond Project Home

Home > Bond Project > What's Happening at Schools? > Casey Middle School  
Casey Middle School 
Casey Middle School 
Casey Middle School
2410 13th Street
Boulder, Colorado 80304
720.561.5446
http://bvsd.org/schools/Casey
Original construction date: 1924
Report Updated:  11/17/2009 
Project Details
Principal: Alison Boggs  

Project Manager: Lou Novak    

Architect: RB+B  

Contractor: Saunders Construction

Original Project Budget:  $31,122,650
Supplemental Funding
from City of Boulder:
(to be reimbursed to BVSD for appropriate LEED certification expenses)
  $1,800,000
Revised Budget:  $32,922,650

Casey Middle School project expenditures to date

Bond Program expenditures to date

 

Design Advisory Team:

Staff
Kathryn Singey
Lester Lurie
Brenda Lotterhos
Molly Hoverstock
Audra Blackledge
Miguel Villalon
Alison Boggs
Cynthia Jarmon
Cathie Williamson
Carrie Hausfather
Ed Campisi

Parents
Richard Foy
Elene Mooney
Don Price
Doug Young
Judy Amabile
Lisa Van Leuwen-Hall
Kristin Fitzgerrell
Anthony Gonzales

City
James Hewatt
Jonathan Koehn
 

Student
Leanna Landis

Community
John Koval
Thomas Volckhausen
Judy Amabile
Celeste Landry
Julie Husband

Contact the DAT: DAT.Casey@bvsd.org

Meeting Schedule:
2007
September 10, 17, 24
October 1, 8, 15, 22, 29
November 5, 26
December 3, 10, 17

2008
January 14, 28
February 4, 11, 25
March 31
May 30, 7:30 a.m., Casey library
September 12, 7 a.m.

DAT Meeting minutes and handouts

 

Project Timeline

Scheduled Milestones
uSD (schematic design) due 03/08; Completed 03/08
uCM/GC selection 07/07; Completed 07/07
uDD (design development) drawings due 06/08, adjusted to 07/08; Completed 07/08
uCD (construction documents) due 10/08; Completed 10/08
uGMP (guaranteed maximum price) due 12/09; adjusted to 01/09; Completed 02/09
uConstruction scheduled 01/09 - 06/10; Under construction

u= Design phase
u= Construction bidding
u= Construction phase

General construction schedule
Preconstruction activities: December 2008
Salvage materials: December 2008
Contractor mobilization: January 2009
Asbestos abatement: Jan. 12 - Feb. 2009
Building demolition: Jan. - Mar. 2009
Begin construction: March 2009
Building structure: May - Sept. 2009
Building enclosure: Sept. - Dec. 2009
Certificate of occupancy: June 2010

Project Status

Project status:

  • Masonry, exterior brickwork continues
  • Roofing is nearing completion with gravel surfacing yet to be completed
  • Mechanical, Electrical, and Plumbing
  • Drywall and painting
  • Restoration of the historic façade continues
  • Site concrete (walls and walks)
  • Synthetic Turf continues subject to weather conditions
  • Wood windows and aluminum storefronts
  • Voice/Data system installation started November 2nd.
  • Temporary heat is being provided building wide.    

Critical issues:

None at this time.

Budget issues: 

None at this time.

Schedule status:

Project is 60 percent complete and on schedule to complete by May 2010.  

Preliminary mechanical commissioning will start in January with the geothermal system.   Final commissioning and installing of owner supplied equipment and furnishings will take place following Saunders completing their work.

Sign up for Casey Construction News

Read more about the geothermal system at the new Casey Middle School

View the Casey Middle School construction webcam 

  Read about the LEED components of this project

 Project Design Update

Concept Design Drawings of the New Casey Middle School

 

 


Construction photos - February 2009


 
Crews dig wells for the geo thermal system


 

 

Construction photos - March 2009

 

 


 
Construction photos - April 2009

 

 

 

 

 

 


Construction photos - May 2009

 

 

 

 

 

 

 

 

 



Aerial photos - May 29, 2009

 

 

Construction photos - June 2009

 

 

 

 

 

 

 

 

 


Construction photos - July 2009

 

 

 

 

 

 

 

 

 

 

Aerial photos - July 2009

 

 

 

 

 

 

 

Aerial photos - August 2009

 

 

 

 

 


Construction photos - September 2009

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Aerial photos - September 2009

 

 

 

 

 


Construction photos - October 2009

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Aerial photos - October 2009

 

 

 

 

 

 

 

 

 

 

Scope of Work

Facility Condition Assessment (FCA):

  • No work is anticipated due to the planned demolition of the existing building

Program Compatibility Assessment (PCA):

  • A new middle school, meeting the Educational Specifications, will be constructed on the site

Multi-Use Outdoor Facilities (MUOF):

  • New synthetic turf playfield and multi-use hard paved areas will be provided on the site

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce cost
  • Classroom spaces to use multimedia, projectors, and sound enhancement

 

 

 Casey Construction News

New Casey begins to take shape
After months of nearly weekly meetings, this week the Casey Middle School design advisory team got to see the concepts and ideas they’ve been discussing take shape in the schematic design. The schematic design is still preliminary in nature and subject to change, but it is a good representation of how the final building will likely look and function.

Read more . . .

Casey project featured in the Daily Camera

 

 

Going green to get gold at Casey

Solar panels, geothermal heating and cooling, daylighting, preferred parking for carpool and low-emissions vehicles, low flow water fixtures and covered bike racks – these were just a few of the green building strategies discussed at the LEED design charrette for the new Casey Middle School building held Feb. 27.

 

Read more . . .


Integrating old and new
In their design process, the DAT looked at the possibility of preserving the 1924 portion of the building and considered it in the context of other priorities including the building’s ability to meet its educational priority, efficient site utilization, sustainability (LEED), safety/accessibility, and schedule and cost effectiveness. The team considered three different options: 1) preserving and adapting the 1924 building and adding onto it, 2) preserving just the west and south facades of the 1924 building and integrating them into the new construction; and 3) demolishing the existing building and starting with a clean slate. Last week, the design advisory team came to a strong consensus decision to proceed with option 2, preserving the west and south facades.

Letter to parents about the design decision

Going Green
Thanks to a generous financial contribution from the City of Boulder, we will be able to make the new Casey a high performance building in terms of energy efficiency and resource conservation. We are pursuing the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) gold certification. LEED is the industry-recognized, voluntary rating system that defines high-performing green buildings.

More information about LEED schools
What else is green in the 2006 Bond Program?

Casey students and staff to move to Platt during construction
The District made the decision to temporarily house the Casey school community at Platt Middle School during the period of construction from January 2009 through May 2010. Next year, classes at Casey will begin at 8:30 and end at 3:20.

Questions and Answers about the relocation
Preguntas y Respuestas sobre el Traslado de la Escuela Intermedia Casey a la Escuela Intermedia Platt
Update on relocation planning
¡Novedades Sobre Casey en Platt!