Fairview High School 
 
Fairview High School
1515 Greenbriar Blvd.
Boulder, Colorado 80305
720.561.3100
http://bvsd.org/schools/Fairviewhs
Original construction date: 1971
Report Updated:  9/30/2009 
Project Details

Principal: Donald Stensrud

Project Manager (building): Steve Schumacher

Architect (building): RTA, Inc.

Architect (MUOF/athletics): Davis Partnerships

Project Manager (MUOF/athletics): Joe Gierlach

Contractor: Golden Triangle

Project Budget (total):
Original Total Project Budget

$10,910,579 

Original building budget

$10,056,974

Transfer from athletics

+$110,564

Revised building budget

$10,167,538

Original athletics budget

$853,605

Transfer to building budget

-$110,564

Revised athletics budget

$743,040

Revised Total Project Budget

 $10,910,579

Fairview High expenditures to date

Bond Program expenditures to date

 

Design Advisory Team (building):

Staff
Don Stensrud, Principal
Frank Lee, AP – Athletic Director
Jim Butterfield – Asst. Principal
Carol Diebel
Rick Harig
Merritt Lealman
Jenny McCarthy
Amy Paa-Rogers
Ed Parada

Parents
Ron Diederichsen
Linda Kaboth
John Salisbury
Anne Knoor
Billy O’Donnell

Students
Morgan Kois
Chytanya Kompala

Design Advisory Team (MUOF/athletics):

Staff
Michele DeBerry
Frank Lee
Rick Harig
Stan Jozwiak
Dave Kreutzman
Tom McCartney

Contact the DAT: DAT.Fairview@BVSD.org

Project Timeline

Scheduled Milestones (building)
uSD (schematic design) due 08/07; Completed 08/07
uDD (design development) drawings due 10/07; Completed 10/07
uCD (construction documents) due 01/08; Completed 02/08
uHard bid scheduled 03/08; Completed 03/08
uConstruction scheduled 03/08 - 08/09; adjusted to 06/08 - 08/09; Substantially Completed 08/09
   Renovation of the 300 level will occur June-Aug. 2010

u= Design phase
u= Construction bidding
u= Construction phase

Scheduled Milestones (MOUF/athletics)
Construction scheduled 04/08 - 08/08; Complete

Project Status

Project status (building):

Project phases 1 and 2 are complete. All spaces are occupied. 

The DAT reconvened to revise plans for the 300 level due to the change in the scope of work. Construction documents for the new design are complete. This work will take place in the summer of 2010.

Project status (MUOF/Athletics):

Athletic improvements are complete.

Critical issues (building):

None

Critical issues (MUOF/athletics):

None

 Budget status (building):

On budget

Budget status (MUOF/athletics):

On budget

Schedule status:

Construction of 300 level has been delayed to summer 2010.  

Scope of Work

  Read about the green building practices in this project

Facility Condition Assessment (FCA):  Planned implementation (FCA):
  • Communication systems improvements 
  • Replace existing intercom system. 
  • Ventilation improvements
  • Replace selected aged rooftop HVAC equipment
  • Irrigation system upgrades 
  • Field irrigation repairs and replacement of controls. 
  • Interior finishes upgraded (i.e. ceiling tiles, carpet, wall finishes, etc.) 
  • Will upgrade finishes in limited areas, priority to be determined by DAT. 
  • Upgrade electrical distribution 
  • Electrical improvements as required for classrooms. 
  •  Replace boilers
  • Replace existing boilers. 
  • Interior Signage Program 
  • Consistent interior signage throughout. 

 

Program Compatibility Assessment (PCA):  Planned Implementation (PCA):
  • Remodel 300 level, including replacement of Teen Parenting Center with other classrooms (amended by the Board of Education December 9, 2008)
  • Remodel 300 level 
  • Remodel 700 level 
  • Remodel 700 level 
  • Remodel counseling and senior balcony 
  • Remodel counseling and remodel senior balcony into administrative space. Remodel administrative offices on 800 level. 
  • Construct additional classrooms 
  • Construct additional classrooms adjacent to the 600 level 
  • Replace lockers
  • Replace lockers removed as part of remodel of senior balcony. 
Multi-Use Outdoor Facilities (MUOF):  Planned Implementation (MUOF):
  • Field house facility at the playfields with water and toilet facilities 
  • New drinking fountain to be installed at the tennis courts. 
  • Extend water and sewer utilities to the sports field 
  • New field house metal building with a CMU block accent at the exterior walls at a height of 3’-4” to be constructed and new drinking fountain to be installed at the tennis courts. 
  • Upgrade condition of the softball fields 
  • Replace outfield wire mesh fence and new wind screen to be installed. Base boards to be added at the fence at the backstop and dugouts at the softball field. The softball field is to be regraded at the transition from the infield dirt to the outfield grass
  • New infield mix is to be added to the softball field. 
  • New bleachers are to be added to the softball field. Extending utility lines from scoreboard to new press box location. Existing gates and signage to be replaced at the track. 
  • Provide additional security fencing and signage at the sports fields 
  • Fencing and signage to be modified and added at the existing football field. Possible alternate available to add a press box at the softball field. Possible alternate available to add a second  team room to the field house.
  • Possible alternate available to extend water utilities to the track. 
Information Technology (IT): 
  • Upgrade WAN to provide capacity to support applications with high bandwidth demands 
  • Extend WAN to building, upgrade head end equipment. 
  • Upgrade LANs to provide reliable and responsive access to data, research, and information 
  • Upgrade existing LAN distribution. 
  • Implement VoIP to enhance communications capabilities and reduce cost 
  • Install new VoIP telecommunications system. 

 Project photos

Renderings of new spaces

 

New addition

 

New student commons

 

New vestibule


Groundbreaking May 12, 2008

 

 

 

 

 

Construction photos - June 2008

 
New addition

 
Demolition of administrative suite

 
Demolition of locker balcony

 
Classroom demolition

 

Construction photos - July 2008

 
New locker bays

 
New student commons and administrative remodel

 
New, more efficient boilers

 
Classroom and office remodels

 
New entryway


Classroom addition foundation 

New field house takes shape

 

 

 


Field house interior

Construction photos - August 2008

 
Walls go up for the new classroom addition

 
Walls go up for the new classroom addition

 
Walls go up for the new classroom addition

 
Walls go up for the new classroom addition

 
New field house is substantially complete

 
New field house is substantially complete

 
Entryway gets a facelift

 
New teachers' lounge

 
Remodeled student lounge, counselors' offices
and post grad center

 
New post grad center

 
New post grad center

 
New student lounge


 Construction photos - November 2008

 
View from new classrooms

 
New addition interior

 
New addition interior

 
New addition exterior

 
New addition exterior

 
New addition interior

 
New student center

 

 
New student center with skylight

 

Project photos - June 2009

 
Remodeled administration office

 
Remodeled administration office

 
New student center with skylight

 

     

 New entryway

 
New classroom addition exterior

 
New classroom addition exterior

 
New classroom addition exterior