Halcyon Middle/Senior
3100 Bucknell Court
Boulder, CO 80305
720-561-4700

http://www.bvsd.org/middle/halcyon/Pages/default.aspx Original construction date: 1955
Report Updated:  9/28/2011
Project Details

Principal: Matthew Dudeck

Project Manager: Lou Novak

Architect: Hutton Architecture Studio 

Contractor: Quinlan Construction

Original Budget:

 $200,000

Transfer from Project Reserve to meet scope

 +$63,425

Total Revised Budet:   $263,425

Halcyon project expenditures

Bond Program expenditures

Halcyon Middle/High School was not included in the original Educational Facilities Master Plan. The project scope of work and budget was created for the school by the Citizens' Bond Oversight Committee and approved by the Board of Education at its April 26, 2011 meeting.

In addition to the funding provided by the Bond Program, $40,000 has been donated by IMPACT, a partnership of agencies that serve children and families with mental health needs.

 

Design Advisory Team (DAT): 

Matthew Dudek, Principal
Kathy Bullington, School Secretary
Susan Bullas, Boulder County Mental Health

 

Project Timeline
The project was completed during the summer of 2011.
Project Status

Project complete.

Project Update for Neighbors

Project photos - September 2011 

 
New exterior paint


New exterior paint 

 
Repaved basketball court

 
New walkway between buildings

 
Lockers were removed from hallways to create more space and solatubes were installed.

 

 
Remodeled time away space

 
Remodeled time away space


Larger counselors offices 


Remodeled principal's office.  

Scope of Work

Facility Condition Assessment (FCA):

  • Address fire code issues
  • Exterior paint
  • Improve circulation in the building
  • Improve access to the cafeteria
  • Move lockers out of corridors
  • Upgrade some finishes including interior paint and carpet
  • Provide daylighting devices 

Program Compatibility Assessment (PCA):

  • Provide private rooms for counseling sessions 

Information Technology (IT): (already funded and implemented)

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs

Multi-Use Outdoor Facilities

  • Repave basketball court

 

 