Front view of Pioneer Elementary School
 
Escuela Bilingue Pioneer
Elementary School
101 E. Baseline Rd.
Lafayette, CO 80026
720.561.7800
http://bvsd.org/schools/Pioneer
Original construction date: 1926
Report Updated:  9/6/2011
Project Details

Principal: Miguel Villalon

Project Manager: John Bollinger

Architect: H&L Architecture

Contractor: W.O. Danielson

Original Project Budget:

 $4,605,385

Transfer from Program Reserve for HVAC improvements 

+$62,253

Transfer from Program Reserve for solatubes, demolition and computer lab

+$70,000

Adjusted Project Budget:    $4,737,638

Escuela Bilingue Pioneer project expenditures

Bond Program expenditures

 

Design Advisory Team (DAT):

Meeting Schedule
Oct. 26, 3-5 p.m.
Nov. 2, 9, 30; 3-5 p.m.
Dec. 7; user group meetings

DAT Meeting Minutes

Contact the DAT

Project Timeline

Scheduled Milestones
uSD (schematic design) due 12/09; Completed 12/09
uDD (design development) drawings due 1/10; Completed 02/10
uCD (construction documents) due 04/10
uConstruction Bid due 05/10
uConstruction Scheduled 06/10 - 08/11; Completed 09/11

u= Design phase
u= Construction bidding
u= Construction phase

Project Status
Project complete.
 
 
New Addition Renderings
 

 

 

 

 

 

 

 

 
 
Project photos - August 2010

 

 

 


Construction photos - November 2010

 

 

 

 

 

 

 

 

 


 

Construction photos - January 2011

 
New entrance lobby


 

 
New conference room

 

 
Corridor in new main office

 

 
New main office

 

 
New administrative suite exterior

 

 
New classroom wing exterior

 


New classroom

 


New classroom

 


New classroom

 


Construction photos - February 2011

 
New office addition exterior

 
New reception area


New conference room

 
New classroom

 

 


Project photos - March 2011

 
New entry foyer


New reception area
 

 
New office space

 
New conference room

 


New kindergarten room 

 

Project photos - June 2011

 
New entry

 

 
New administrative addition

 
Preschool playground

 
Preschool playground

 

 
Classroom remodel


New computer lab 

 
Classroom remodel


Cafeteria will get new flooring 


Third grade classroom remodel

 

 


New preschool classroom

 

 

 

Project photos - July 2011

 
New flooring in cafeteria

 
Covered walkway

 
Covered walkway


New playground
 

Scope of Work

Facility Condition Assessment (FCA):

  • Fire alarm improvements
  • Boiler replacement
  • Electrical service and distribution improvements
  • Roof replacement and repair
  • Restroom improvements and ADA access
  • Selected window replacement
  • Concrete and asphalt replacement and repair
  • Interior Signage Program

Program Compatibility Assessment (PCA):

  • Kindergarten classroom renovation
  • IMC expansion and remodel
  • Expand administration and health space
  • Special Education classroom addition/remodel
  • Music classroom renovation

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs